MASAR

Automated BIE Auditor

BIE Compliance

Overall status

violation

2

pass

2

advisory

1

warning

1

violation

warning

Zonal phasing timeline must match Bid Book p.187 commitment

Zone B foundation works currently 18% behind Bid Book commitment Q2 2026 line.

p. 187 · 4.2 Zonal Phasing·Timeline
advisory

≥ 30% SME participation across construction packages

At 27% — within 3 points of commitment; trending up.

p. 312 · 7.1 Local Economic Impact·SME participation
pass

Quarterly BIE secretariat report must include construction milestones

Q1 2026 submission filed on time; Q2 2026 draft is in review.

p. 441 · 9.3 International Positioning·Reporting cadence
violation

Sustainability Committee meets at least monthly

No Sustainability Committee meeting scheduled in the last 6 weeks.

p. 503 · 11.4 Sustainability Governance·Sustainability
advisory

BIE Paris delegation contact cadence ≥ 1×/month

Last engagement 39 days ago — within advisory window.

p. 442 · 9.3.1 Paris Engagement·Diplomatic protocol
pass

Bid Book deviations must be logged and acknowledged in briefings

2 deviations logged this quarter; both acknowledged in HRH briefings.

p. 92 · 2.4 Transparency Charter·Transparency